- Create a booth that would take the whole fuselage and keep the rest of the workshop free of dust. This would also serve as the paint spray booth later on.
- Make sure I had the appropriate blasting equipment including safety wear and consumables.
- Get some paint stripper just in case.
- Arrange for the AD inspection on the strut attachments at an early stage when the weld clusters had been cleaned up.
The booth was made from white tarpaulin sheet hung from the roof beams with the lights inside the booth. The dimensions were about 20 x 10 feet giving enough room to work around the fuselage. I also have a small extractor fan used to keep the dust down.
I bought a cheep hopper (http://www.northerntooluk.com/sandblasting/sandblasting-accessories/portable-shot-blasting-kit_146993E.html) which holds a 25 Kg bag of grit/bead and utilises my compressor running at about 115 psi. In practice, this would last for about 30-40 minutes before having to be topped up. I also purchased a hood with spare lenses, gauntlets and disposable overalls to wear during the blasting.
I anticipated the blasting would take three days to complete followed by a day to paint the fuselage but as ever it took longer for several reasons. After three days I had completed the initial blasting but there was a lot of paint that just wouldn't come off mainly around the cockpit area.
There was a mixture of paints, what looked like powder coating and some rubberised coating which I decided might come off better if I applied paint stripper. Another day was spent applying the stripper. The paint stripper used was SV-35/PMA formulated specifically for aviation paints (http://www.paint-stripper.co.uk/removall_paint_stripper_aviation.htm) and non-toxic. I left the stripper overnight to be cleaned off the next day. The results looked pretty good. I can recomend this product as it's easy to work with, strips the paint quickly (I was working in neart freezing conditions over winter so it should work very quickly in the summer months) and is easy to dispose of afterwards.
In all the process took about 10 days spread over 4 weeks, but I did loose a week because the weather over here was so bad I couldn't get to the workshop. In hindsight I should have spent more time paint stripping and left the bead blasting just for the final finish but that's what this blog is about, helping you save time through my experiences. I think a realistic timetable for the job would have been 2 days to paint strip, 1 day to clean and 3 days to blast, still a lot of work but very satisfying once completed.
Next time, priming the fuselage.